Update on City Projects to date 12/20/07

Project                                                             Amount Spent to Date 12/20/07

Electrical                                                          $3,600,000

Incubator Building                                           $2,000,000

Street Lights                                                   $1,523,546

Water Tower                                                   $598,000

USDA-Mennonite Housing                                $400,000

Providing Porta-Johns                                      $141,205

Private Property Demo                                     $110,197

Water Well Pumps                                           $99,075

Traffic Signal                                                    $86,700

Tree Removal                                                   $63,240

Warning Sirens                                                $54,677

Concrete Removal                                           $53,112

Temporary Big Well Shop                                 $46,204

Permanent Water System                               $45,587

Final Debris Clean Up                                      $45,456

Well House Repair                                           $37,522

Temporary Water System                                $27,528

Road Equipment Bldg Repair                            $25,828

Replace Street Signs                                        $21,287